  1. A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products.

    The finance and production teams want a way to view individual raw material consumption costs in the ledger.

    You need to add a production group to control postings to the ledger.

    What should you do?

    • Create a production group for the finished good item
    • Update the cost of the generic finished good item
    • Create a production pool for the finished good item
    • Create a new Bill of materials with alternate costs for the raw material
  2. HOTSPOT

    A company implements Dynamics 365 Supply Chain Management.

    Production orders are generated for products directly from projects. You create the following production order:

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q02 016
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q02 016

    Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q02 017 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q02 017 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q02 017 Answer
  3. HOTSPOT

    A customer produces light projection toys for holiday decorations throughout the year.

    You must implement Bills of material (BOMs) for the product lifestyle. The solution must meet the following requirements:

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 018
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 018

    You need to create a BOM for each phase.

    Which BOM types should you use? To answer, select the appropriate configuration options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 019 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 019 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 019 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q03 019 Answer
  4. A manufacturing company uses advanced warehouse management functionality for a new warehouse.

    After releasing a production order, you observe that the warehouse work for raw material picking was not generated.

    You need to go through the warehouse management setup to determine what is missing.

    What three setup configurations must you validate? Each correct answer presents part of the solution.

    NOTE: Each correct selection is worth one point.

    • Work template for raw material picking
    • Wave template
    • Directive codes
    • Confirm the production output location on your resource group
    • Location directive for raw material picking
  5. DRAG DROP

    A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

    Employees spend considerable time cleaning and setting up machines in a specific area between production orders. You must group production activities to optimize cleaning and set up time.

    You need to set up the system.

    In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q05 020 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q05 020 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q05 020 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q05 020 Answer
  6. DRAG DROP

    A company makes lubricants and greases used in the automotive industry. The company plans to implement Dynamics 365 Supply Chain Management.

    The system must meet the following requirements:

    – Schedule the batch production of products.
    – Plan for inventory fluctuations of ingredients that are used across different products.
    – Schedule delivery of amounts of proprietary compounds used during production from vendors to keep production runs on schedule and eliminating excess stock on hand or delayed production.

    The company is starting the initial setup of their Dynamics 365 environment.

    You need to perform the initial setup of the environment.

    Where would you need to set up the following items? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q06 021 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q06 021 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q06 021 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q06 021 Answer
  7. A company makes lubricants and greases used in the automotive industry.

    They are planning to use Dynamics 365 Supply Chain Management to make products whose characteristics can be tracked throughout the production process and are associated with the packaged product.

    You need to identify which production methodology to use.

    Which production methodology should you use?

    • Discrete manufacturing
    • Lean manufacturing
    • Process manufacturing
    • Job shop manufacturing
  8. DRAG DROP

    A company plans to account for indirect costs related to materials used to manufacture products.

    The items used to manufacture products have surcharge rates that depend on the type of product being used.

    You need to set up the costing sheet to include surcharges for specific items.

    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q08 022 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q08 022 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q08 022 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q08 022 Answer
  9. A company produces multiple products that require an installation kit that includes 50 components.

    The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOM kit that includes all 50 components, but you do not want it to produce a separate production order.

    You need to set up the product BOM for the finished good.

    What should you do?

    • Select Phantom on the engineering fast tab on the kit item
    • Change the coverage group on the kit item to Manual
    • Change the line type to Phantom
    • Change the line type to Pegged supply
  10. DRAG DROP

    A company overstates on-hand raw materials due to the time it takes to post raw materials when production orders are processed.

    All items used to manufacture finished goods must be consumed when a finished good is reported as finished. You must not change all bill of materials lines to use the option of flushing principal.

    You need to ensure that all production orders consume raw materials at Report as finished.

    Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q10 023 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q10 023 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q10 023 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q10 023 Answer
  11. HOTSPOT

    A company makes engine parts used in the automotive industry.

    They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 Supply Chain Management to help support the Bill of Materials (BOM) product lifecycle for engineering version control.

    You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.

    What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q11 024 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q11 024 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q11 024 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q11 024 Answer
  12. HOTSPOT

    A company implements Dynamics 365 Finance and Operations.

    You need to ensure that cost roll-ups and sales price calculations are configured for the scenario.

    Which options should you use? To answer, select the appropriate options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q12 025 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q12 025 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q12 025 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q12 025 Answer
  13. DRAG DROP

    You are the product definition manager for a car manufacturing company. You set up and maintain the production configuration models used at the company.

    You must build a new configuration model and include constraints in the model.

    You need to determine which constraint type to use for each scenario.

    Which constraint type should you use? To answer, drag the appropriate constraint types to the correct scenarios. Each constraint type may be used once, more than once, or not at all. You may need to drag the split bat between panes or scroll to view content.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q13 026 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q13 026 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q13 026 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q13 026 Answer
  14. You are the production supervisor in charge of setting effective cost prices for the labor force in a manufacturing company.

    It is the end of the year and the labor rates have been recalculated based on new salary data.

    You need to update the effective labor costs for all labor groups.

    Which element must be updated?

    • cost groups
    • shared category
    • resource group
    • cost category
    • production orders
  15. DRAG DROP

    A company produces custom-made bicycles that offer many different configurations.

    Your standard bicycle, B-0001, is made with many common components such as a frame and wheels. Customers can choose between two frames: F-0001 or F-0009. Wheel W-0001 is only compatible with frame F-0001.

    You create the following configuration groups: Frames, Wheels.

    You need to ensure that users can only select valid combinations of frames and wheels.

    In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q15 027 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q15 027 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q15 027 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q15 027 Answer
  16. A company produces pipe at certain fixed lengths.

    The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

    You need to configure the resources to account for these different products.

    What should you do?

    • Configure the Data/Hour option on the Capacity unit field on the resource.
    • Build capability related to length and assign to the appropriate resources.
    • Create a resource group for each length.
    • Create a resource for each length.
  17. DRAG DROP

    A company uses separate finished good item numbers for size variations of the same product.

    The company wants to minimize the number of variously-sized items that are created.

    You need to perform the setup to allow variants in size to the product master.

    Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q17 028 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q17 028 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q17 028 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q17 028 Answer
  18. A company manufactures and sells speaker boxes. The speaker boxes can be silver or black with a basic or upgraded wiring harness assembly.

    The speaker box must be created in the item master so the variables for colors and harness type can be assigned at order entry.

    You need to create a new item that supports multiple variables.

    What should you do?

    • Create a new product. Select predefined variant as the configuration technology
    • Create a new product. Select constraint-based configuration as the configuration technology
    • Create a new product master. Select predefined variant as the configuration technology
    • Create a new product master. Select constraint-based configuration as the configuration technology
  19. HOTSPOT

    An inventory control clerk manages adjustments in inventory.

    Some adjustments have a cost impact. Other adjustments must be posted to a specific ledger account or must be registered in inventory.

    You need to configure the system.

    Which journal types should you use? To answer, select the appropriate options in the answer area.

    NOTE: Each correct selection is worth one point.

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q19 029 Question
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q19 029 Question

    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q19 029 Answer
    MB-320 Microsoft Dynamics 365 Supply Chain Management, Manufacturing Part 02 Q19 029 Answer
  20. Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

    After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

    A company uses Dynamics 365 Supply Chain Management to manage production configuration.

    A product designer creates a remote control toy that can be purchased with different tire sizes.

    Sales representatives need to perform product configuration for the custom tire variants when they create a new order.

    Solution: Select the custom tire size when filling out the item requirement line.