CAPM : Certified Associate in Project Management (PMI-100) : Part 04
-
Which process determines the risks that may affect the project and documents their characteristics?
- Control Risks
- Plan Risk Management
- Plan Risk Responses
- Identify Risks
Explanation:
Process: 11.2 Identify Risks
Definition: The process of determining which risks may affect the project and documenting their characteristics.
Key Benefit: The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events.Inputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Quality management plan
5. Human resource management plan
6. Scope baseline
7. Activity cost estimates
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental factors
13. Organizational process assets
Tools & Techniques
1. Documentation reviews
2. Information gathering techniques
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgmentOutputs
1. Risk register11.2.3.1 Risk Register
The primary output from Identify Risks is the initial entry into the risk register. The risk register is a document in which the results of risk analysis and risk response planning are recorded. It contains the outcomes of the other risk management processes as they are conducted, resulting in an increase in the level and type of information contained in the risk register over time. The preparation of the risk register begins in the Identify Risks process with the following information, and then becomes available to other project management and risk management processes:
– List of identified risks. The identified risks are described in as much detail as is reasonable. A structure for describing risks using risk statements may be applied, for example, EVENT may occur causing IMPACT, or If CAUSE exists, EVENT may occur leading to EFFECT. In addition to the list of identified risks, the root causes of those risks may become more evident. These are the fundamental conditions or events that may give rise to one or more identified risks. They should be recorded and used to support future risk identification for this and other projects.
– List of potential responses. Potential responses to a risk may sometimes be identified during the Identify Risks process. These responses, if identified in this process, should be used as inputs to the Plan Risk Responses process. -
An example of a group decision-ma king technique is:
- Nominal group technique.
- Majority.
- Affinity diagram.
- Multi-criteria decision analysis.
-
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
- mitigate
- accept
- transfer
- avoid
Explanation:11.5.2.1 Strategies for Negative Risks or Threats
Three strategies, which typically deal with threats or risks that may have negative impacts on project objectives if they occur, are: avoid, transfer, and mitigate. The fourth strategy, accept, can be used for negative risks or threats as well as positive risks or opportunities. Each of these risk response strategies have varied and unique influence on the risk condition. These strategies should be chosen to match the risk’s probability and impact on the project’s overall objectives. Avoidance and mitigation strategies are usually good strategies for critical risks with high impact, while transference and acceptance are usually good strategies for threats that are less critical and with low overall impact. The four strategies for dealing with negative risks or threats are further described as follows:– Avoid. Risk avoidance is a risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact. It usually involves changing the project management plan to eliminate the threat entirely. The project manager may also isolate the project objectives from the risk’s impact or change the objective that is in jeopardy. Examples of this include extending the schedule, changing the strategy, or reducing scope. The most radical avoidance strategy is to shut down the project entirely. Some risks that arise early in the project can be avoided by clarifying requirements, obtaining information, improving communication, or acquiring expertise.
– Transfer. Risk transference is a risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response. Transferring the risk simply gives another party responsibility for its management—it does not eliminate it. Transferring does not mean disowning the risk by transferring it to a later project or another person without his or her knowledge or agreement. Risk transference nearly always involves payment of a risk premium to the party taking on the risk. Transferring liability for risk is most effective in dealing with financial risk exposure. Transference tools can be quite diverse and include, but are not limited to, the use of insurance, performance bonds, warranties, guarantees, etc. Contracts or agreements may be used to transfer liability for specified risks to another party. For example, when a buyer has capabilities that the seller does not possess, it may be prudent to transfer some work and its concurrent risk contractually back to the buyer. In many cases, use of a cost-plus contract may transfer the cost risk to the buyer, while a fixed-price contract may transfer risk to the seller.
– Mitigate. Risk mitigation is a risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk. It implies a reduction in the probability and/or impact of an adverse risk to be within acceptable threshold limits. Taking early action to reduce the probability and/or impact of a risk occurring on the project is often more effective than trying to repair the damage after the risk has occurred. Adopting less complex processes, conducting more tests, or choosing a more stable supplier are examples of mitigation actions. Mitigation may require prototype development to reduce the risk of scaling up from a bench-scale model of a process or product. Where it is not possible to reduce probability, a mitigation response might address the risk impact by targeting linkages that determine the severity. For example, designing redundancy into a system may reduce the impact from a failure of the original component.
– Accept. Risk acceptance is a risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs. This strategy is adopted where it is not possible or cost-effective to address a specific risk in any other way. This strategy indicates that the project team has decided not to change the project management plan to deal with a risk, or is unable to identify any other suitable response strategy. This strategy can be either passive or active. Passive acceptance requires no action except to document the strategy, leaving the project team to deal with the risks as they occur, and to periodically review the threat to ensure that it does not change significantly. The most common active acceptance strategy is to establish a contingency reserve, including amounts of time, money, or resources to handle the risks. -
An output of the Plan Quality Management process is:
- A process improvement plan.
- Quality control measurements.
- Work performance information.
- The project management plan.
Explanation:Process: 8.1 Plan Quality Management
Definition: The process of identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with quality requirements and/or standards.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how quality will be managed and validated throughout the project.Inputs
1. Project management plan
2. Stakeholder register
3. Risk register
4. Requirements documentation
5. Enterprise environmental factors
6. Organizational process assets
Tools & Techniques
1. Cost-benefit analysis
2. Cost of quality
3. Seven basic quality tools
4. Benchmarking
5. Design of experiments
6. Statistical sampling
7. Additional quality planning tools
8. Meetings
Outputs
1. Quality management plan
2. Process improvement plan
3. Quality metrics
4. Quality checklists
5. Project documents updates -
A project manager should document the escalation path for unresolved project risks in the:
- Change control plan
- Stakeholder register
- Risk log
- Communications management plan
Explanation:10.1.3.1 Communications Management Plan
The communications management plan is a component of the project management plan that describes how project communications will be planned, structured, monitored, and controlled. The plan contains the following information:
– Stakeholder communication requirements;
– Information to be communicated, including language, format, content, and level of detail;
– Reason for the distribution of that information;
– Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable;
– Person responsible for communicating the information;
– Person responsible for authorizing release of confidential information;
– Person or groups who will receive the information;
– Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases;
– Resources allocated for communication activities, including time and budget;
– Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level;
– Method for updating and refining the communications management plan as the project progresses and develops;
– Glossary of common terminology;
– Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; and
– Communication constraints usually derived from a specific legislation or regulation, technology, and organizational policies, etc.The communications management plan can also include guidelines and templates for project status meetings, project team meetings, e-meetings, and e-mail messages. The use of a project website and project management software can also be included if these are to be used in the project
-
Which process in Project Time Management includes reserve analysis as a tool or technique?
- Estimate Activity Resources
- Sequence Activities
- Estimate Activity Durations
- Develop Schedule
Explanation:Process: 6.5 Estimate Activity Durations
Definition: The process of estimating the number of work periods needed to complete individual activities with estimated resources.
Key Benefit: The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Activity resource requirements
5. Resource calendars
6. Project scope statement
7. Risk register
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Group decision-making techniques
6. Reserve analysis
Outputs
1. Activity duration estimates
2. Project documents updates6.5.2.6 Reserve Analysis
Duration estimates may include contingency reserves, sometimes referred to as time reserves or buffers, into the project schedule to account for schedule uncertainty. Contingency reserves are the estimated duration within the schedule baseline, which is allocated for identified risks that are accepted and for which contingent or mitigation responses are developed. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account for this unknown amount of rework.
As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in schedule documentation.
[..]
Estimates may also be produced for the amount of management reserve of time for the project. Management reserves are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown-unknowns” that can affect a project. Management reserve is not included in the schedule baseline, but it is part of the overall project duration requirements. Depending on contract terms, use of management reserves may require a change to the schedule baseline. -
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
- Enhance
- Share
- Exploit
- Accept
Explanation:
11.5.2.2 Strategies for Positive Risks or Opportunities
Three of the four responses are suggested to deal with risks with potentially positive impacts on project objectives.
The fourth strategy, accept, can be used for negative risks or threats as well as positive risks or opportunities. These strategies, described below, are to exploit, share, enhance, and accept.
– Exploit. The exploit strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring the opportunity definitely happens. Examples of directly exploiting responses include assigning an organization’s most talented resources to the project to reduce the time to completion or using new technologies or technology upgrades to reduce cost and duration required to realize project objectives.
– Enhance. The enhance strategy is used to increase the probability and/or the positive impacts of an opportunity. Identifying and maximizing key drivers of these positive-impact risks may increase the probability of their occurrence. Examples of enhancing opportunities include adding more resources to an activity to finish early.
– Share. Sharing a positive risk involves allocating some or all of the ownership of the opportunity to a third party who is best able to capture the opportunity for the beneft of the project. Examples of sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint ventures, which can be established with the express purpose of taking advantage of the opportunity so that all parties gain from their actions.
– Accept. Accepting an opportunity is being willing to take advantage of the opportunity if it arises, but not actively pursuing it. -
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
- Expert judgment.
- Analytical techniques.
- Earned value management.
- Group decision-making techniques.
Explanation:
7.1.2.2 Analytical Techniques
Developing the cost management plan may involve choosing strategic options to fund the project such as:
self-funding, funding with equity, or funding with debt. The cost management plan may also detail ways to finance project resources such as making, purchasing, renting, or leasing. These decisions, like other financial decisions affecting the project, may affect project schedule and/or risks.
Organizational policies and procedures may influence which financial techniques are employed in these decisions. Techniques may include (but are not limited to): payback period, return on investment, internal rate of return, discounted cash flow, and net present value. -
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
- Timing
- Methodology
- Risk categories
- Budgeting
Explanation:
11.1.3.1 Risk Management Plan
The risk management plan is a component of the project management plan and describes how risk management activities will be structured and performed. The risk management plan includes the following:
– Methodology. Defines the approaches, tools, and data sources that will be used to perform risk management on the project.
Roles and responsibilities. Defines the lead, support, and risk management team members for each type of activity in the risk management plan, and clarifes their responsibilities.
– Budgeting. Estimates funds needed, based on assigned resources, for inclusion in the cost baseline and establishes protocols for application of contingency and management reserves.
Timing. Defines when and how often the risk management processes will be performed throughout the project life cycle, establishes protocols for application of schedule contingency reserves, and establishes risk management activities for inclusion in the project schedule. -
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
- Negative
- Zero
- Positive
- Free
-
A reward can only be effective if it is:
- Given immediately after the project is completed.
- Something that is tangible.
- Formally given during project performance appraisals.
- Satisfying a need valued by the individual.
-
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
- Nominal group technique
- Idea/mind mapping
- Affinity diagram
- Brainstorming
Explanation:5.2.2.4 Group Creativity Techniques
Several group activities can be organized to identify project and product requirements. Some of the group creativity techniques that can be used are:
– Brainstorming. A technique used to generate and collect multiple ideas related to project and product requirements. Although brainstorming by itself does not include voting or prioritization, it is often used with other group creativity techniques that do.
Nominal group technique. A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.
– Idea/mind mapping. A technique in which ideas created through individual brainstorming sessions are consolidated into a single map to reflect commonality and differences in understanding, and generate new ideas.– Affinity diagram. A technique that allows large numbers of ideas to be classified into groups for review and analysis.
– Multicriteria decision analysis. A technique that utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.
-
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
- Bottom-up
- Parametric
- Analogous
- Three-point
-
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
- Direct
- Interactive
- Pull
- Push
Explanation:
10.1.2.4 Communication Methods
There are several communication methods that are used to share information among project stakeholders.
These methods are broadly classifed as follows:
– Interactive communication. Between two or more parties performing a multidirectional exchange of information. It is the most effcient way to ensure a common understanding by all participants on specified topics, and includes meetings, phone calls, instant messaging, video conferencing, etc.
– Push communication. Sent to specific recipients who need to receive the information. This ensures that the information is distributed but does not ensure that it actually reached or was understood by the intended audience. Push communications include letters, memos, reports, emails, faxes, voice mails, blogs, press releases, etc.
– Pull communication. Used for very large volumes of information, or for very large audiences, and requires the recipients to access the communication content at their own discretion. These methods include intranet sites, e-learning, lessons learned databases, knowledge repositories, etc.
The choices of communication methods that are used for a project may need to be discussed and agreed upon by the project stakeholders based on communication requirements; cost and time constraints; and familiarity and availability of the required tools and resources that may be applicable to the communications process. -
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
- Cost variance (CV)
- Cost performance index (CPI)
- Budget at completion (BAC)
- Variance at completion (VAC)
Explanation:
CPI = EV / AC -
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
- Direct and Manage Project Work
- Develop Project Management Plan
- Plan Quality Management
- Monitor and Control Project Work
Explanation:Process: 4.2. Develop Project Management Plan
Definition: The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project’s integrated baselines and subsidiary plans may be included within the project management plan.
Key Benefit: The key benefit of this process is a central document that defines the basis of all project work.Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project management plan4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes.
Project baselines include, but are not limited to:
– Scope baseline (Section 5.4.3.1),
– Schedule baseline (Section 6.6.3.1), and
– Cost baseline (Section 7.3.3.1).Subsidiary plans include, but are not limited to:
– Scope management plan (Section 5.1.3.1),
– Requirements management plan (Section 5.1.3.2),
– Schedule management plan (Section 6.1.3.1),
– Cost management plan (Section 7.1.3.1),
– Quality management plan (Section 8.1.3.1),
– Process improvement plan (Section 8.1.3.2),
– Human resource management plan (Section 9.1.3.1),
– Communications management plan (Section 10.1.3.1),
– Risk management plan (Section 11.1.3.1),
– Procurement management plan (Section 12.1.3.1), and
– Stakeholder management plan (Section 13.2.3.1).
Among other things, the project management plan may also include the following:
– Life cycle selected for the project and the processes that will be applied to each phase;
– Details of the tailoring decisions specified by the project management team as follows:
○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
– Description of how work will be executed to accomplish the project objectives;
– Change management plan that documents how changes will be monitored and controlled;
– Configuration management plan that documents how Configuration management will be performed;
– Description of how the integrity of the project baselines will be maintained;
– Requirements and techniques for communication among stakeholders; and
– Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
-
Inputs to the Plan Schedule Management process include:
- Organizational process assets and the project charter,
- Enterprise environmental factors and schedule tools.
- Time tables and Pareto diagrams.
- Activity attributes and resource calendars.
Explanation:2.1.4 Organizational Process Assets
Organizational process assets are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization. They include any artifact, practice, or knowledge from any or all of the organizations involved in the project that can be used to perform or govern the project. The process assets also include the organization’s knowledge bases such as lessons learned and historical information. Organizational process assets may include completed schedules, risk data, and earned value data. Organizational process assets are inputs to most planning processes. Throughout the project, the project team members may update and add to the organizational process assets as necessary. Organizational process assets may be grouped into two categories: (1) processes and procedures, and (2) corporate knowledge base.6.1 Plan Schedule Management
Definition: The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Schedule management plan -
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
- Identify Risks
- Control Risks
- Perform Quantitative Risk Analysis
- Perform Qualitative Risk Analysis
Explanation:
11.2.2.6 SWOT Analysis
This technique examines the project from each of the strengths, weaknesses, opportunities, and threats (SWOT) perspectives to increase the breadth of identified risks by including internally generated risks. The technique starts with identification of strengths and weaknesses of the organization, focusing on either the project, organization, or the business area in general. SWOT analysis then identifies any opportunities for the project that arise from organizational strengths, and any threats arising from organizational weaknesses. The analysis also examines the degree to which organizational strengths offset threats, as well as identifying opportunities that may serve to overcome weaknesses.Process: 11.2 Identify Risks
Definition: The process of determining which risks may affect the project and documenting their characteristics.
Key Benefit: The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events.Inputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Quality management plan
5. Human resource management plan
6. Scope baseline
7. Activity cost estimates
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental factors
13. Organizational process assets
Tools & Techniques
1. Documentation reviews
2. Information gathering techniques
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgmentOutputs
1. Risk register11.2.3.1 Risk Register
The primary output from Identify Risks is the initial entry into the risk register. The risk register is a document in which the results of risk analysis and risk response planning are recorded. It contains the outcomes of the other risk management processes as they are conducted, resulting in an increase in the level and type of information contained in the risk register over time. The preparation of the risk register begins in the Identify Risks process with the following information, and then becomes available to other project management and risk management processes:
– List of identified risks. The identified risks are described in as much detail as is reasonable. A structure for describing risks using risk statements may be applied, for example, EVENT may occur causing IMPACT, or If CAUSE exists, EVENT may occur leading to EFFECT. In addition to the list of identified risks, the root causes of those risks may become more evident. These are the fundamental conditions or events that may give rise to one or more identified risks. They should be recorded and used to support future risk identification for this and other projects.
– List of potential responses. Potential responses to a risk may sometimes be identified during the Identify Risks process. These responses, if identified in this process, should be used as inputs to the Plan Risk Responses process. -
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
- Project Risk Management
- Project Human Resource Management
- Project Scope Management
- Project Stakeholder Management
Explanation:
PROJECT STAKEHOLDER MANAGEMENT
Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution. Stakeholder management also focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicting interests and fostering appropriate stakeholder engagement in project decisions and activities. Stakeholder satisfaction should be managed as a key project objective. -
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
- Stakeholder register
- Scope management plan
- Stakeholder management plan
- Project charter
Explanation:5.2.1.5 Stakeholder Register
Described in Section 13.1.3.1. The stakeholder register is used to identify stakeholders who can provide information on the requirements. The stakeholder register also captures major requirements and main expectations stakeholders may have for the project.13.1.3.1 Stakeholder Register
The main output of the Identify Stakeholders process is the stakeholder register. This contains all details related to the identified stakeholders including, but not limited to:
– Identification information. Name, organizational position, location, role in the project, contact information;
– Assessment information. Major requirements, main expectations, potential influence in the project, phase in the life cycle with the most interest; and
Stakeholder classification. Internal/external, supporter/neutral/resistor, etc.The stakeholder register should be consulted and updated on a regular basis, as stakeholders may change—or new ones identified—throughout the life cycle of the project.
Process: 5.2 Collect Requirements
Definition: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
Key Benefit: The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.
Inputs
1. Scope management plan
2. Requirements management plan
3. Stakeholder management plan
4. Project charter
5. Stakeholder register
Tools & Techniques
1. Interviews
2. Focus groups
3. Facilitated workshops
4. Group creativity techniques
5. Group decision-making techniques
6. Questionnaires and surveys
7. Observations
8. Prototypes
9. Benchmarking
10. Context diagrams
11. Document analysis
Outputs
1. Requirements documentation
2. Requirements traceability matrix