CAPM : Certified Associate in Project Management (PMI-100) : Part 41

  1. Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?

    • Communications methods
    • Reporting systems
    • Forecasting methods
    • Variance analysis

    Explanation:
    Reporting Systems. Facilities, processes, and procedures used to generate or consolidate reports from one or more information management systems and facilitate report distribution to the project stakeholders.

  2. Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?

    • Activities
    • Milestone list
    • Work breakdown structure (WBS)
    • Work packages
  3. Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

    • Estimate Activity Durations
    • Control Schedule
    • Sequence Activities
    • Develop Schedule
    Explanation:

    Process: 6.6 Develop Schedule
    Definition:  The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
    Key Benefit: The key benefit of this process is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities.

    Inputs
    1. Schedule management plan
    2. Activity list
    3. Activity attributes
    4. Project schedule network diagrams
    5. Activity resource requirements
    6. Resource calendars
    7. Activity duration estimates
    8. Project scope statement
    9. Risk register
    10. Project staff assignments
    11. Resource breakdown structure
    12. Enterprise environmental factors
    13. Organizational process assets
    Tools & Techniques
    1. Schedule network analysis
    2. Critical path method
    3. Critical chain method
    4. Resource optimization techniques
    5. Modeling techniques
    6. Leads and lags
    7. Schedule compression
    8. Scheduling tool
    Outputs
    1. Schedule baseline
    2. Project schedule
    3. Schedule data
    4. Project calendars
    5. Project management plan updates
    6. Project documents updates

  4. Which process group contains the processes performed to finalize all activities?

    • Planning Process Group
    • Executing Process Group
    • Monitoring and Controlling Process Group
    • Closing Process Group
    Explanation:
    • Closing Process Group. Those processes performed to finalize all activities across all Process Groups to formally close the project or phase.
  5. Which schedule development technique modifies the project schedule to account for limited resources?

    • Human resource planning
    • Fast tracking
    • Critical chain method
    • Rolling wave planning
    Explanation:
    6.6.2.3 Critical Chain Method
    The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method. To do so, the critical chain method introduces the concept of buffers and buffer management. The critical chain method uses activities with durations that do not include safety margins, logical relationships, and resource availability with statistically determined buffers composed of the aggregated safety margins of activities at specified points on the project schedule path to account for limited resources and project uncertainties. The resource-constrained critical path is known as the critical chain.
  6. Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?

    • Portfolio manager
    • Project sponsor
    • Project manager
    • Project management office
    Explanation:
    Sponsor. A sponsor is the person or group who provides resources and support for the project and is accountable for enabling success. The sponsor may be external or internal to the project manager’s organization. From initial conception through project closure, the sponsor promotes the project. This includes serving as spokesperson to higher levels of management to gather support throughout the organization and promoting the benefits the project brings. The sponsor leads the project through the initiating processes until formally authorized, and plays a significant role in the development of the initial scope and charter. For issues that are beyond the control of the project manager, the sponsor serves as an escalation path. The sponsor may also be involved in other important issues such as authorizing changes in scope, phase-end reviews, and go/no-go decisions when risks are particularly high. The sponsor also ensures a smooth transfer of the project’s deliverables into the business of the requesting organization after project closure.
  7. Which standard examines an enterprise’s project management process capabilities?

    • PMBOK Guide
    • The Standard for Program Management.
    • Organizational Project Management Maturity Model “OPM3”
    • The Standard for Portfolio Management
  8. Which tool or technique is used to develop a project charter?

    • Project manager information systems
    • Expert judgment
    • Change control meetings
    • Brainstorming
    Explanation:

    4.1.2.1 Expert Judgment
    Expert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:
    – Other units within the organization,
    – Consultants,
    – Stakeholders, including customers or sponsors,
    – Professional and technical associations,
    – Industry groups,
    – Subject matter experts (SME), and
    – Project management office (PMO).

    Process: 4.1. Develop Project Charter
    Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
    Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.

    Inputs
    1. Project statement of work
    2. Business case
    3. Agreements
    4. Enterprise environmental factors
    5. Organizational process assets
    Tools & Techniques
    1. Expert judgment
    2. Facilitation techniques
    Outputs
    1. Project charter

  9. Which tool or technique measures performance of the project as it moves from project initiation through project closure?

    • Resource leveling
    • Parametric measuring
    • Pareto chart
    • Earned value
    Explanation:
    7.4.2.1 Earned Value Management
    Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance measurement baseline, which helps the project management team assess and measure project performance and progress. It is a project management technique that requires the formation of an integrated baseline against which performance can be measured for the duration of the project.
  10. Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face?

    • Co-location team
    • Virtual team
    • Departmental team
    • Consultant team
  11. Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

    • Project sponsor and project manager
    • Project sponsor and functional manager
    • Project manager and project team
    • Project team and functional manager
  12. Who is responsible for developing the project management plan and all related component plans?

    • Project team
    • Portfolio manager
    • Project manager
    • Project management office
    Explanation:

    4.2.3.1 Project Management Plan
    The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes.
    Project baselines include, but are not limited to:
    – Scope baseline (Section 5.4.3.1),
    – Schedule baseline (Section 6.6.3.1), and
    – Cost baseline (Section 7.3.3.1).

    Subsidiary plans include, but are not limited to:
    – Scope management plan (Section 5.1.3.1),
    – Requirements management plan (Section 5.1.3.2),
    – Schedule management plan (Section 6.1.3.1),
    – Cost management plan (Section 7.1.3.1),
    – Quality management plan (Section 8.1.3.1),
    – Process improvement plan (Section 8.1.3.2),
    – Human resource management plan (Section 9.1.3.1),
    – Communications management plan (Section 10.1.3.1),
    – Risk management plan (Section 11.1.3.1),
    – Procurement management plan (Section 12.1.3.1), and
    – Stakeholder management plan (Section 13.2.3.1).
    Among other things, the project management plan may also include the following:
    – Life cycle selected for the project and the processes that will be applied to each phase;
    – Details of the tailoring decisions specified by the project management team as follows:
    ○ Project management processes selected by the project management team,
    ○ Level of implementation for each selected process,
    ○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
    ○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
    – Description of how work will be executed to accomplish the project objectives;
    – Change management plan that documents how changes will be monitored and controlled;
    – Configuration management plan that documents how Configuration management will be performed;
    – Description of how the integrity of the project baselines will be maintained;
    – Requirements and techniques for communication among stakeholders; and
    – Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.

    The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.

  13. Who is responsible for reviewing change requests and approving or rejecting the change requests?

    • Change control board
    • Project manager
    • Project management office
    • Project sponsor
    Explanation:
    Change Control Board (CCB). A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.
  14. Who MUST know when a risk event occurs so that a response can be implemented?

    • Customers
    • Project sponsors
    • Project management team
    • Insurance claims department.
  15. Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?

    • Functional manager
    • Project manager
    • Functional manager supported by the project manager
    • Project management office
  16. Within project integration management, the statement of work (SOW) references which aspects of the project?

    • Strategic plan, business need, and product scope description
    • Contract, enterprise environmental factors, and organizational process assets
    • Business plan, project management plan, and project schedule
    • Product lifecycle, business objective, and management strategy
    Explanation:

    4.1.1.1 Project Statement of Work Page 67

    The project statement of work (SOW) is a narrative description of products, services, or results to be delivered by a project. For internal projects, the project initiator or sponsor provides the statement of work based on business needs, product, or service requirements. For external projects, the statement of work can be received from the customer as part of a bid document, (e.g., a request for proposal, request for information, or request for bid) or as part of a contract. The SOW references the following:

    – Business need. An organization’s business need may be based on a market demand, technological advance, legal requirement, government regulation, or environmental consideration. Typically, the business need and the cost-benefit analysis are contained in the business case to justify the project.

    – Product scope description. The product scope description documents the characteristics of the product, service, or results that the project will be undertaken to create. The description should also document the relationship between the products, services, or results being created and the business need that the project will address.

    – Strategic plan. The strategic plan documents the organization’s strategic vision, goals, and objectives and may contain a high-level mission statement. All projects should be aligned with their organization’s strategic plan. Strategic plan alignment ensures that each project contributes to the overall objectives of the organization.

  17. Which tool or technique is used in the Develop Project Management Plan process?

    • Pareto diagram
    • Performance reporting
    • SWOT analysis
    • Expert judgment
  18. The review of a seller’s progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

    • Work performance information.
    • Inspections and audits.
    • A contract change control system.
    • Procurement performance reviews.
  19. Which statement summarizes the role of the change control board?

    • The change control board is responsible for presenting the change for approval
    • The change control board will analyze the change impact in terms of cost and schedule
    • The change control board is responsible for managing the change management and configuration management systems
    • The change control board is responsible for reviewing and approving changes to the project
    Explanation:
    Reference: https://blog.masterofproject.com/change-control-board/
  20. A contractor has provided hands-on training to a team member on new equipment that has been purchased as part of the project. The team member has acquired key insight and experience on the new equipment.

    What is this an example of?

    • Explicit knowledge
    • Formal education
    • Tacit knowledge
    • Lessons learned
Subscribe
Notify of
guest
0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments