What charts and figures should project managers use during the Perform Quantitative Risk Analysis process?
- Tornado diagrams and influence diagrams
- Detectability bubble charts and probability and impact matrix
- Hierarchical charts and burndown charts
- Flow charts and responsible, accountable, consult, and inform (RACI) charts
-
Recognition and rewards are tools and techniques of which process?
- Develop Team
- Manage Team
- Control Resources
- Plan Resource Management
Explanation:
Reference: https://4squareviews.com/2018/06/15/6th-edition-pmbok-guide-process-9-4-develop-team-tools-and-techniques/
-
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
- Create Work Breakdown Structure (WBS)
- Create Scope Baseline
- Collect Requirements
- Define Scope
-
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders.
What is this an example of?
- Informal communication
- Internal communication
- Formal communication
- Horizontal communication
-
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
- Push communication
- Pull communication
- Interactive communication
- Stakeholder communication
-
A project report completed an earned value (EV) of US $45 for work with an actual cost (AC) of US $40. What is the cost performance index (CPI)?
- 0.88
- 1.12
- 0.58
- 1.58
-
A project manager is writing a document that obligates the seller to provide the specified products, services, or results, and obligates the buyer to compensate the seller. This document represents a legal relationship that is subject to remedy in the courts.
Which document is described?
- General terms
- Contract agreement
- Change request
- Statement of work
Explanation:Reference: http://www.forum.izenbridge.com/viewtopic.php?t=1603 -
What is the difference between quality metrics and quality measurements?
- Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process
- Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes
- Quality metrics and measurements are the same concept
- Quality metrics is the general objective and the measurements are the specific objectives
Explanation:Reference: https://project-management-knowledge.com/definitions/q/quality-metrics/ -
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
- Leadership management
- Technical project management
- Strategic management
- Business management
Explanation:Reference: https://books.google.com.pk/books?id=3XQwDgAAQBAJ&pg=PA185&lpg=PA185&dq=project+manager+competency+is+displayed+through+the+knowledge,+skills,+and+behaviors+related+to+specific+domains+of+project,+program,+and+portfolio+management&source=bl&ots=0Dc0IXYmoj&sig=ACfU3U01VAogFp6oEdNW5FlikLvT5nybSg&hl=en&sa=X&ved=2ahUKEwjXt42Oy_3hAhXd8uAKHe11B54Q6AEwBHoECAkQAQ#v=onepage&q=project%20manager%20competency%20is%20displayed%20through%20the%20knowledge%2C%20skills%2C%20and%20behaviors%20related%20to%20specific%20domains%20of%20project%2C%20program%2C%20and%20portfolio%20management&f=false -
Which of the following technology platforms is most effective for sharing information when managing virtual project teams?
- Video conferencing
- Audio conferencing
- Shared portal
- Email/chat
-
Which of the following is an example of the objective of a quality audit?
- Identify nonconformities, shortcomings, and gaps
- Verify solution effectiveness
- Perform data gathering
- Conduct retrospective
Explanation:Reference: https://project-management-knowledge.com/definitions/q/quality-audits/ -
A firm contracted an event management company to conduct the annual sales day event. The agreement that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract is this?
- Time and material (T&M)
- Fixed price incentive fee (FPIF)
- Cost plus fixed fee (CPFF)
- Cost plus award fee (CPAF)
-
Which tool is critical for the team to adapt to a high variability benefit project?
- Colocation
- Collaboration
- Flexibility
- Specialization
-
What organizational asset can influence the Plan Risk Management process?
- Corporate policies and procedures for social media, ethics, and security
- Organizational risk policy
- Stakeholder register templates and instructions
- Organizational communication requirements
-
What is the role of project management in terms of organizational strategy?
- Project management aligns initiatives, prioritizes work, and provides resources
- Project management provides the strategic vision for an organization to achieve its goals
- Project management enables the achievement of organizational goals and objectives
- Project management harmonizes components and controls interdependencies to realize specific benefits
-
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
- Diversity background
- Stakeholder’s relationships
- Technical expertise
- Knowledge management
-
Due to new market conditions a five-year project requires a full revision of project objectives. Which components of the stakeholder engagement plan need to be updated?
- Scope and impact of change to stakeholders
- Project scope and stakeholder goals
- Engagement level of key stakeholders
- Stakeholder expectations for the project
-
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
- Predictive
- Adaptive
- A mix
- Agile
-
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
- Interactive
- Push
- Verbal
- Oral
-
What is the first step in the Stakeholder Management process?
- Plan Stakeholder Engagement
- Identify Stakeholders
- Manage Stakeholder Responsibility
- Monitor Stakeholder Activity