In addressing a risk that has low potential impact and relatively high cost of mitigation or reduction, which strategy will accept the risk and its consequences?
- risk sharing
- risk retention
- risk reduction
- risk avoidance
Answers Explanation & Hints:
There are four potential strategies for responding to risks that have been identified: Risk avoidance – Stop performing the activities that create risk. |