What output of the Conduct Procurements process is also an input to the Control Procurements process?
- Agreements
- Change requests
- Source selection criteria
- Bid documents
-
In which Project Cost Management process is work performance data included?
- Plan Cost Management
- Estimate Costs
- Determine Budget
- Control Costs
-
A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager’s sphere of influence does this represent?
- The project
- The organization
- Professional discipline
- Across disciplines
-
What should a project manager reference to understand where responsibility, accountability, and authority reside within a company?
- Project charter
- Scope of work
- Project management system
- Organizational system
-
DRAG DROP
Match the role with its corresponding job description.
-
DRAG DROP
A project manager is reviewing the different tools and techniques used to perform a quantitative risk analysis. Match the tool and techniques with the appropriate result.
-
What is the main benefit of the lessons learned register?
- Provides validation requirements
- Supplies monitoring and reporting methods
- Improves the performance of future projects
- Documents the status of deliverables and project results
-
What is both an input and output of the Control Quality process and is updated as a result of this process?
- Lessons learned register
- Risk register
- Enterprise environmental factors (EEFs)
- Root cause analysis
-
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
- Resource availability
- Infrastructure
- Academic research
- Corporate knowledge base
Explanation:Reference: https://www.deepfriedbrainproject.com/2018/07/enterprise-environmental-factors-vs-organizational-process-assets.html -
What is an example of an emerging trend in procurement management?
- Online technologies enable projects to postpone ordering long lead items until the items are needed.
- Online technologies allow a project’s progress to be viewed by all stakeholders to build better relations.
- Online procurement tools provide buyers with multiple sources to advertise to sellers.
- Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.
-
What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?
- Project Cost Management
- Project Integration Management
- Project Risk Management
- Project Schedule Management
-
What key component of the project charter defines the conditions for closing a project phase?
- Purpose
- Approval requires
- Exit criteria
- High-level requirements
-
DRAG DROP
Match the process with its corresponding process group.
Explanation:Reference: https://projectmanagementacademy.net/articles/five-traditional-process-groups/ -
What major skill sets comprise the PMI Talent Triangle?
- Technical project management, technology management, and strategic and business management
- Technical project management, leadership, and strategic and business management
- Leadership, operational management, and technical project management
- Organizational management, operational management, and technology management
Explanation:Reference: https://www.pmi.org/learning/training-development/talent-triangle#:~:text=The%20ideal%20skill%20set%20%E2%80%94%20the,%E2%80%94%20and%20now%2C%20digital%20skills. -
What three strategies are used to respond to threats?
- Escalate, accept, and mitigate
- Accept, share, and avoid
- Escalate, transfer, and exploit
- Mitigate, accept, and prioritize
-
Which is an example of a technical project management skill?
- Managing a project schedule
- Developing a project delivery strategy
- Establishing a project team
- Understanding organizational objectives
-
What is the primary benefit of the Manage Quality process?
- Increases the probability of meeting quality objectives
- Enhances the performance of the product being created
- Defines quality roles and responsibilities
- Ensures that the project is completed as originally planned
-
What characteristic of servant leadership supports resource management in an agile environment?
- Lecturing
- Controlling
- Measuring
- Coaching
-
What tool or technique will establish expected behaviors for project team members?
- Ground rules
- Decision making
- Power/influence grid
- Stakeholder engagement assessment matrix
-
What is the primary purpose of Project Scope Management?
- Determining and managing stakeholder needs.
- Controlling the status of the product scope and managing changes to its baseline.