PMI-ACP : PMI Agile Certified Practitioner : Part 17
-
The 80/20 rule is also known as what law?
- Little Law
- Pareto’s Law
- Mohr’s Law
- The Law of Averages
-
Pareto Analysis is the exercise of determining what 40% of functionality can be delivered with 60% of the effort.
- True
- False
-
The length of time to recover the cost of a project investment is the:
- Net Present Value
- Payback Period
- Earned Value
- ROI
-
An archetypal user of a systems is called a(n):
- Super user
- Admin
- Persona
- UX engineer
-
Personas are used in Agile requirements to depict which type of user?
- Real users
- Fictitious users
- Super users
- Beta testers
-
When is Planning Poker used?
- During backlog prioritization
- As part of Pareto Analysis
- During User Story sizing and estimating
- As part of the Daily Stand-up
-
Process Tailoring is the iterative approach implementing your SDLC process.
- True
- False
-
Product roadmaps are more accurate the closer we get to an actual release.
- True
- False
-
Which is the process of continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available as the project progresses?
- Process Tailoring
- Pareto Analysis
- Progressive Elaboration
- Open Space Planning
-
What is a change made to the internal structure of software to make it easier to understand and cheaper to modify without changing its observable behavior?
- Pair Programming
- Continuous Improvement
- Test Driven Development
- Refactoring
-
Refactoring is a key way of preventing technical debt.
- True
- False
-
Which Agile estimation technique is based upon relative sizing?
- Ideal time
- Bottom up
- Story points
- Little’s Law
-
What kind of User Story is written to provide an opportunity to research a solution in order to provide an estimate?
- Sprint Story
- Persona Story
- Spike Story
- Needle Story
-
DRAG DROP
Sequence the activities that occur in a Retrospective meeting.
Explanation:
1 – Set the Stage
2 – Gather Data
3 – Generate Insights
4 – Decide What We Do
5 – Close the Retrospective -
Triple Nickels is a technique used in what kind of meeting?
- Sprint Planning
- Daily Scrum
- Sprint Retrospective
- XP Planning Game
-
Who is responsible for managing ROI in Agile projects?
- The Project Sponsor
- The Product Owner
- The Agile Project Manager
- The Scrum of Scrums Master
-
The purpose of the Scrum of Scrums is to perform what function?
- To increase knowledge of Agile within the organization
- To provide dashboard reporting to executives
- To manage cross-team dependencies working on the same project or product
- To ensure team building and staff development occurs
-
Which one is NOT one of the 5 common risk areas mitigated by Agile?
- Intrinsic schedule flaw
- Specification breakdown
- Scope creep
- Stakeholder apathy
- Personnel loss
- Productivity variation
-
DRAG DROP
In what order do you select requirements to work on in a risk adjusted backlog?
Explanation:
High Risk High Value
Low Risk High Value
Low Risk Low Value
High Risk Low Value -
Which Agile method promotes the practice of risk-based Spike or Spike solutions?
- Scrum
- AgileUP
- ADSM
- Extreme Programming