Refer to the exhibit. Which two conclusions can be drawn from the output? (Choose two.)

CCNA 2 v7 SRWE Final Exam Answers 30
CCNA 2 v7 SRWE Final Exam Answers 30
  • The port channel ID is 2.
  • The bundle is fully operational.
  • The port channel is a Layer 3 channel.
  • The load-balancing method used is source port to destination port.
  • The EtherChannel is down.
Explanation & Hint:

Based on the output from the show etherchannel summary command in the exhibit, the following two conclusions can be drawn:

  1. The port channel ID is 2.
    • The output shows “Group 1” and “Po2” which indicates the port-channel interface ID is 2. The number after “Po” typically represents the port-channel ID.
  2. The EtherChannel is down.
    • Both ports Fa0/1 and Fa0/2 have the flag “(D)” next to them, which, according to the flag legend in the output, stands for “down”. Additionally, the port-channel Po2 also has an “(SD)” flag, with “S” meaning “layer2” (which by itself doesn’t indicate a down state), but “D” meaning “down”. The combination indicates that the EtherChannel is not currently operational.

The output does not provide enough information to conclude that the port channel is a Layer 3 channel or what load-balancing method is used, and the fact that the EtherChannel is down precludes it from being fully operational.

For more Questions and Answers:

CCNA 2 v7 – SRWE v7.02 Final Exam Answers Full 100%

Subscribe
Notify of
guest
0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments