• Post author:
  • Post category:Blog
  • Reading time:1 mins read
  • Post last modified:June 12, 2024

Mark is the project manager of the HAR Project. The project is scheduled to last for eighteen months and six months already passed. Management asks Mark that how often the project team is participating in the risk reassessment of this project. What should Mark tell management if he is following the best practices for risk management?

  • At every status meeting of the project team, project risk management is an agenda item.
  • Project risk management happens at every milestone.
  • Project risk management has been concluded with the project planning.
  • Project risk management is scheduled for every month in the 18-month project.
Subscribe
Notify of
guest
0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments